Incident Resolved: CTIM-2415
CJ plant has confirmed the documents are correct and will continue with the customs process for the manifest. This incident is now contained. CTIM to provide a critical level postmortem in the coming days.
Please contact CTIM or see ticket for more details.
UPDATE:
Support teams have provided the updated manifest files for the CJ plant. Awaiting confirmation from the plant that these files are correct. Next update in 30 minutes.
UPDATE:
Additional teams are being requested to assist. Awaiting their response to continue troubleshooting. Next update in 1 hour or sooner.
UPDATE:
Support teams have found this manifest may need to be updated manually to proceed with fulfillment. Awaiting next steps from the support teams. Next update in 30 minutes.
New Incident: CTIM-2415
Priority: Critical
Escalation sent to: Fulfillment: Logistics: Squirtle for review.
CTIM is investigating an issue at the CJ plant where production is observing issues with a manifest showing no information or 0 cost. Engaging support teams to investigate at critical priority. Next update in 30 minutes or sooner.