Vista

System displays the correct data but the labels are not printing for shipping

解決済み

Incident Resolved: CTIM-1702
Support Teams have contained or resolved the issue. Please contact MIS PBM or see ticket for more details.

更新済み

UPDATE:

The investigation revealed to a recent network change by the networking team that caused the issue by blocking printer requests. The networking team confirmed they had made a firewall rule change that was blocking these requests. Once the firewall rule was adjusted, stations began printing labels again without needing QZ Tray installed. Issue will be considered contained once all shipping labels are generated.

更新済み

UPDATE:

Various teams are being engaged to investigate further, including Viper support and the former teams, as the root cause is still unclear. Next update when we have new findings or max in 1 hour.

更新済み

UPDATE:
Escalation sent to: Fulfillment: Plant Optimizations/NPI

Support team reviewed the sessions and everything appears fine on their end. Since the shipments are being created successfully and the call to the label printing service is sent, shipping seems to be functioning properly. Currently the plant is hard down. Requesting Viper support team to investigate this further. Next update in max 30 minutes.

更新済み

UPDATE:

Restarted the VistaPrint label printer service in Viper and awaiting results from a local plant IT to confirm resolution before escalating to Viper support. Next update when we hear back from them or max in 30 minutes

更新済み

UPDATE:
Escalation sent to: Fulfillment: Logistics: Gengar

Adding Support team to assist with the investigation further. Next update once once findings are available or max in 30 minutes.

更新済み

UPDATE:

Support team is able to generate labels without any issues. The plant is verifying to confirm if the issue persists. Next update within 30 minutes.

更新済み

UPDATE:

The relevant Support team is online and actively investigating the issue with high priority. Next update in max 30 minutes.

検証中

New Incident: CTIM-1702
Plant: WND
Priority: Critical
Escalation sent to: Fulfillment: Logistics Support for review.