North America

Orders are getting routed to VEN instead of WND

更新済み

UPDATE:

The team informed us that this is a routing issue, which means nothing can be fixed at the product configuration level — it is working as expected. A CCM fix is currently being tested. The next update will be provided after we hear back from the test.

更新済み

UPDATE:

The Vista team has again encountered a similar issue, with 60 orders and 128 items stuck in Venlo. We are awaiting a response from the Vista Logistics team for an update on this issue. The next update will be provided within a maximum of 2 hours.

更新済み

UPDATE:

No additional reports of problems after the config change. We will wait to confirm with Vista teams. Next update once they’ve been able to observe the order routing trend to determine whether the fix was successful (possible by EoD or tomorrow AM).

更新済み

UPDATE:

Vista team have increased the carrier not preferred cost from € 100.00 to € 250.00 this should better avoid shipping other products to the US.

更新済み

UPDATE:

Vista logistics team have added US & CA for paper bags shipping to the US and Canada which might have triggered this issue. still investigation is ongoing. Next update in max 1 hour.

更新済み

UPDATE:

The team is still investigating the incident affecting WND orders being routed to Venlo. The issue is being handled at high priority. The next update will be provided within 1 hour.

更新済み

UPDATE:
Escalation sent to: PCD: Product Operations

Paging product operations team for further assistance on this issue.

更新済み

UPDATE:
Escalation sent to: PCD: Product Operations

Adding Product operations team for further assistance on this issue. Next update in max 1 hour.

更新済み

UPDATE:
Escalation sent to: PCD: Dispatch Squad

The Support team informed us that routing is handled one level above by IDP (Item Delivery Possibilities), which, according to Cortex information owners, is managed by the Dispatch team. Hence, we are adding them for further assistance.

更新済み

UPDATE:

The team is still investigating the incident affecting WND orders being routed to Venlo. The issue is being handled at high priority. The next update will be provided within 1 hour.

検証中

New Incident: CTIM-2059
Priority: High
Escalation sent to: Fulfillment: Logistics: Labe for review.
Support team is currently investigating at high priority an incident affecting WND, where a few orders are being routed to VEN even though they should be routed to WND. The next update will be provided within 1 hour.